Newark Trial Team Obtains Affirmance of Summary Judgment for General Contractor Client
January 21, 2025 —
Lewis Brisbois NewsroomNewark, N.J. (December 31, 2024) - Days after
obtaining an Appellate Division victory affirming a “no cause” jury verdict, Newark Partner Afsha Noran and Managing Partner Colin Hackett obtained a
second appellate court victory affirming a trial court's dismissal of a complaint against another firm client, a general contractor.
The team had previously obtained summary judgment at the trial level on the grounds plaintiff could not establish a prima facie case against the client. The plaintiff appealed the grant of summary judgment and dismissal of her claim to the Appellate Division.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Federal District Court Addresses Material Misrepresentation in First Party Property Damage Claim
August 26, 2024 —
James M. Eastham - Traub LiebermanIn Pittsfield Dev. LLC v. Travelers Indem. Co., 2024 U.S. Dist. LEXIS 117530 (N.D. Ill. July 3, 2024), the United States District Court for the Northern District of Illinois addressed an alleged material misrepresentation by an insured during the course of the adjustment of a water loss claim at an insured property. Subsequent to a pipe burst event which caused damage to a number of the floors in the insured building, the insured submitted a claim to Travelers and also submitted, with the assistance of a retained public adjuster, a damage estimate of the damages at the property. Included within the estimate submitted by the insured was a line item for "Lead Paint & Asbestos Removal" with a corresponding dollar amount of $1,140,000. It was this line item which formed the basis of Travelers' claim of misrepresentation.
At his deposition, the public adjuster testified that the $1,140,000 figure was an oral estimate received over the phone from an asbestos remediation company. Travelers disputed the testimony and contended that no such estimate was ever provided. For support, Travelers pointed to deposition testimony from a remediation company employee that while rough estimates were occasionally given verbally, the largest over the phone estimate she could recall was in the $20,000-$25,000 range. It was also disputed that the company would ever provide an oral quote of that magnitude sight unseen, especially since the largest project the remediation company had ever completed was less than $250,000.
Read the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
ASCE Statement on Hurricane Milton and Environmental Threats
October 15, 2024 —
Feniosky Peña-Mora, P.E., President - American Society of Civil EngineersWASHINGTON, DC. – On the heels of the tragic damage caused by Hurricane Helene throughout the Southeast, Floridians were struck by another major hurricane, Milton, less than two weeks later. Our hearts go out to those impacted again by this storm through property damage, lack of water access, power outages, or worse, loss of life, all before getting a chance to recover from Helene. Civil engineers are dedicated to protecting the public with projects that can lessen the impacts of these storms, and we are eager to help communities rebuild as quickly as possible following events like Milton and Helene.
Although we do not yet know the full scope of destruction caused by Hurricane Milton, severe weather, including compound flooding events, are increasing regularly and pose a great risk to our safety and economic vitality. While so many eyes are fixated on hurricanes impacting the Southeast, wildfires are burning across several western states, including the Elk Fire in Wyoming, the largest wildfire the Bighorn National Forest has experienced in more than a century, now spanning over 75,000 acres as the region is experiencing unusually hot and dry weather and strong winds that are helping this fire to spread rapidly. The climate impacts we are accustomed to – wildfires in the West and hurricanes in the Southeast – are getting stronger, and now environmental challenges are occurring in areas we wouldn't suspect, such as Hurricane Helene striking mountain communities in Western North Carolina that have been labeled as "climate safe-havens," and Texas dealing with annual winter storms.
ASCE is a leader in codes and standards development and has created an
easy-to-understand toolkit for legislators and the public to learn the benefits of these up-to-date standards and determine when and how to adopt them, making our built environment more resilient to natural catastrophes. ASCE's flagship standard,
ASCE/SEI 7-22, recently underwent the most significant update to its
flooding chapter to ensure structures following this standard are prepared for 500-year flood events.
FEMA Offers Recovery Tips for California Wildfire Survivors
January 14, 2025 —
FEMAWASHINGTON -- While fire suppression activities are still ongoing in parts of Southern California, affected individuals and families are taking steps toward recovery.
FEMA is helping people jumpstart their recovery. You may be eligible for FEMA assistance, even if you have insurance. More than $5.3 million so far are in the hands of survivors to help pay for emergency supplies like food, water and baby formula as well as to replace personal property and pay for a temporary place to stay. Below are tips to help Californians recover from the historic wildfires.
If your primary home was affected by the fires, FEMA may be able to help you cover certain costs – like paying for essential items, finding a place to stay, replacing personal property or making basic repairs to your home. However, FEMA assistance is designed to help you if you do not have insurance or if your insurance policies don't cover basic needs. If you have insurance, you should file a claim as soon as possible and be ready to provide your coverage information when applying to FEMA.
There are several ways to apply for FEMA assistance:
To view an accessible video about how to apply visit:
FEMA Accessible: Registering for Individual Assistance or
en Español.
Protecting Expert Opinions: Lessons Regarding Attorney-Client Privilege and Expert Retention in Construction Litigation
August 19, 2024 —
David McLain - Higgins, Hopkins, McLain & Roswell, LLCThe Hill Hotel Owner LLC v. Hanover Insurance Company case has garnered attention due to its implications on the scope of attorney-client privilege in construction litigation. This blog post delves into the project’s background, the ensuing litigation, and the intricate work undertaken by attorneys and experts, highlighting the potential pitfalls associated with assumptions about privilege protections.
Background of the Project
Hill Hotel Owner LLC initiated a construction project in Boulder, Colorado, which included building a basement-level parking garage with an 18” thick concrete slab floor. The project utilized “void form,” a cardboard underlayment intended to create a gap between the foundation and the underlying soil. Unfortunately, the void form became wet and collapsed under the weight of the fresh concrete, causing considerable damage, and necessitating millions of dollars in remediation costs.
Read the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Court Retained Jurisdiction to Enforce Settlement Under Code of Civil Procedure Section 664.6 Despite Dismissal of Complaint
October 21, 2024 —
Garret Murai - California Construction Law BlogAttorneys will commonly add a Code of Civil Procedure section 664.6 provision in their settlement agreements to ensure that courts have continuing jurisdiction to enforce the terms of a settlement, as opposed to having to file a new complaint in the event of a breach of a settlement agreement.
Oral settlements before a trial court are also enforceable under Section 664.6, but as discussed in Eagle Fire and Water Restoration, Inc. v. City of Danuba, Case No. F086052 (May 30, 2024), in cases involving a complaint and multiple cross-complaints, questions can arise as to whether a trial court has in fact retained jurisdiction under Section 664.6 to enforce an oral settlement and even what the terms of the settlement were.
The Eagle Fire Case
Eagle Fire and Water Restoration, Inc. was hired by the City of Dinuba to reroof the City’s police station and courthouse building. The contract was for approximately $500,000. Before completion of the project, a rainstorm caused significant water damage to the interior of the building. The City incurred over $330,000 in clean-up and repair costs and withheld approximately $319,000 from Eagle as an offset.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
An Overview of the New EPA HVAC Refrigerant Regulations and Its Implications for the Construction Industry
September 30, 2024 —
Stefanie A. Salomon, Nadia Ennaji & Ali Heyat - Peckar & Abramson, P.C.The U.S. Environmental Protection Agency (EPA) recently announced a series of significant changes to the rules governing the use of refrigerants in heating, ventilation, and air conditioning (HVAC) systems. These changes, which were promulgated under the American Innovation and Manufacturing (AIM) Act, are designed to phase down the use of hydrofluorocarbons (HFCs), a class of potent greenhouse gases.
The AIM Act: A Game-Changer for HVAC Industry
The recent changes to refrigerant regulations by the EPA signify a substantial shift in environmental policy that will have profound implications for the construction industry. For the construction industry, this means a transition to next-generation technologies that do not rely on HFCs. The AIM Act’s sector-based restrictions will affect a wide range of equipment, including refrigeration and air conditioning systems integral to building design and function.
Starting January 1, 2025, the manufacturing or importing of any product in specified sectors that uses a regulated substance with a global warming potential of 700 or greater is prohibited (40 C.F.R. § 84.54(a)). The specified sectors listed include R-410A, the most common refrigerant used in the HVAC industry. The installation of systems using a regulated substance with a global warming potential of 700 or greater in specified sectors is allowed until January 1, 2026, provided that all system components are manufactured or imported before January 1, 2025. See 40 C.F.R. § 84.54 (c). “Installation” of an HVAC system is defined as the completion of assembling the system’s circuit, including charging it with a full charge, such that the system can function and is ready for its intended purpose. See 40 C.F.R. § 84.52.
Reprinted courtesy of
Stefanie A. Salomon, Peckar & Abramson, P.C. and
Nadia Ennaji, Peckar & Abramson, P.C.
Ms. Salomon may be contacted at ssalomon@pecklaw.com
Ms. Ennaji may be contacted at nennaji@pecklaw.com
Read the full story...
“You Can’t Make Me Pay!”
January 28, 2025 —
Daniel Lund III - LexologySeveral years ago, Louisiana enacted a law prescribing a mandamus proceeding for unpaid contract sums purportedly owed by a public entity to a contractor – Louisiana Revised Statute 38:2191. The statute tackles both progress payments and final payment, distinguishing between the two and allowing withholding of a progress payment when there is “reasonable cause” to do so.
On the other hand, at least one Louisiana appellate decision held on the topic of final payment: once a final payment amount is “due” per the statute – based upon passage expiration of the lien period following “formal final acceptance” – the act of making the final payment is purely ministerial and not subject to defenses. According to that court, a defense to payment based on assessed liquidated damages – because the damages were disputed by the contractor – could not trump the essence of the statute allowing the contractor to pursue mandamus to collect the final payment.
More recently, on a public works levee project in Lafourche Parish, a dispute arose during the work concerning the means to secure material for constructing the levees. The net effect of the dispute entailed a major change in the contract price.
Read the full story...Reprinted courtesy of