White House Seeks $310M To Fix Critical San Diego Wastewater Plant
December 04, 2023 —
James Leggate - Engineering News-RecordThe Biden administration’s $55.9-billion
supplemental funding request to Congress for disaster response and other issues includes $310 million for a project to repair and expand the ailing South Bay International Wastewater Treatment Plant in San Diego, Calif. The plant is part of a
repeatedly overwhelmed wastewater treatment system on the U.S.-Mexico border that has allowed untreated sewage flows to foul area beaches.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story...
Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
Construction Litigation Roundup: “Apparently, It’s Not Always Who You Know”
December 16, 2023 —
Daniel Lund III - LexologyA respondent party in a pair of international arbitrations on the losing end of roughly $285,000,000 in adverse awards attacked the awards based upon arbitrator bias.
“If there is one bedrock rule in the law of arbitration, it is that a federal court can vacate an arbitral award only in exceptional circumstances. … The presumption against vacatur applies with even greater force when a federal court reviews an award rendered during an international arbitration.”
Applying the Federal Arbitration Act (according to the court, the international arbitrations were “seated” in the United States and fell under the New York Convention, such that the FAA is required to be the basis for vacatur efforts), the court examined assertions that certain alleged non-disclosures by the panel “concealed information related to the arbitrators’ possible biases and thereby ‘deprived [respondent] of [its] fundamental right to a fair and consensual dispute resolution process.’” The aggrieved party urged that one arbitrator’s undisclosed nomination of another arbitrator to serve as president of another arbitral panel – “a position that sometimes pays hundreds of thousands of dollars” – possibly influenced the second arbitrator to side with the first. Assertions were also levied that the arbitrators’ undisclosed work with the attorneys for the claimant in other arbitrations “allowed them to become familiar with each other, creating a potential conflict of interest.”
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Partner John Toohey is Nominated for West Coast Casualty’s Jerrold S. Oliver Award of Excellence!
March 11, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is honored to share that Newport Beach Partner John Toohey is nominated for West Coast Casualty’s 2024 Jerrold S. Oliver Award of Excellence!
Every year, West Coast Casualty recognizes an individual who is committed, trustworthy, and has contributed years to the betterment of the construction defect community. The award is named after the late Judge Jerrold S. Oliver who is considered a “founding father” in the alternate resolution process in construction claims and litigation. Each year, members of the construction community are asked to nominate individuals who invoke the same spirit as Judge Oliver.
Read the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Build, Baby, Build. But Not Like This, Britain.
March 04, 2024 —
Matthew Brooker - BloombergThe UK needs to do a lot more building. A lack of access to physical and digital connections is holding back the economy, the government says. Besides tackling the housing crisis, the country has to construct more roads, railways, wind farms and reservoirs to open up opportunity and drive productivity. The only problem is that Britain is notoriously inept at delivering infrastructure projects on time and within budget.
The advantage of doing things badly is that at least you get to learn from your mistakes — in theory. Updates this month have offered some illuminating insights into two of the biggest civil-engineering undertakings in the country: High-Speed Rail 2, better known as HS2, and Hinkley Point C, which will be Britain’s first new nuclear power station since 1995. Here are five lessons that can be drawn from the issues encountered by two projects with a combined bill that’s likely to exceed £100 billion ($127 billion):
Don't take budgets too seriously — especially at the start. Fixing an initial budget that was too low may have done much to feed later perceptions that HS2’s costs were spiraling out of control. The original estimate for the expanded train network was set too early and based on “very immature data,” Jon Thompson, appointed executive chair of High Speed 2 Ltd. in February last year, told the House of Commons transport committee. Numbers get more accurate and reliable as work progresses and the quality of information improves. What were viewed as cost blowouts partly reflected this process. The effect was unfortunate, undermining political support for HS2 and providing cover for cutbacks that have reduced the network to a single line between London and Birmingham that fails to fulfill most of its original purpose. To avoid this problem: Stick to a range rather than a single figure, and make sure people understand the uncertainties inherent in early-stage estimates.
Read the full story...Reprinted courtesy of
Matthew Brooker, Bloomberg
Gaps in Insurance Created by Complex Risks
January 22, 2024 —
The Hartford Staff - The Hartford InsightsFrom slips, trips and falls to extreme weather and cyberattacks, businesses are regularly confronted with risks to operations and profitability. In 2023, elevated building costs, increased flooding, and growing ransomware attacks made it compelling for business owners to make sure they had adequate insurance to stay ahead of property and liability exposures. However, if left unchecked, these trends can lead to gaps in coverage. As 2024 approaches, now is the time to assess your risk and collaborate with the right resources to fill any potential voids in insurance.
Economic inflation for example has changed property valuations, which can result in coverage gaps if policyholders have not examined their replacement costs recently.
Read the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights
Unpunished Racist Taunts: A Pennsylvania Harassment Case With No True 'Winner'
December 04, 2023 —
Richard Korman - Engineering News-RecordThe taunts started in the first days of Andre Pryce’s new job, camouflaged as joking. During the nine months of 2019 spent working as a drill rig hand, mostly in the woods in western Pennsylvania, for a contractor that also performs much construction-related drilling, he said coworkers filled his ears with racist insults.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story...
Government Claims Act Does Not Apply to Actions Solely Seeking Declaratory Relief and Not Monetary Relief
March 25, 2024 —
Garret Murai - California Construction Law BlogPerhaps it should come as no surprise, but public entities get special treatment under the law, and when filing a claim against a public entity, in most cases, a claimant is required to file a claim with the public entity before filing suit under the Government Claims Act (Gov. Code §810 et seq.).
But, as the next case demonstrates, that’s not always the case. In Stronghold Engineering Incorporated v. City of Monterey, 96 Cal.App.5th 1203 (2023), the 6th District Court of Appeals examined whether a public works contractor that alleged an extended overhead claim was required to file a Government Claims Act claim before filing suit when its initial complaint was limited to a claim for declaratory relief.
The Stronghold Case
In December 2015, general contractor Stronghold Engineering Incorporated entered into a construction contract with the City of Monterey for the renovation of the City’s conference center and an adjacent city-owned plaza. The construction contract provided that any modification to the construction contract had to be approved by the City through a written change order. No surprise there.
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com